Construction of a qualifying asset is halted for four months because of a labour dispute (not a normal part of the process). Under Ind AS 23, what happens to borrowing costs during the halt?

  1. A. They continue to be capitalised
  2. B. Capitalisation is suspended; they are expensed
  3. C. They are deferred and capitalised when work resumes
  4. D. They are capitalised at half the rate

Correct answer: B. Capitalisation is suspended; they are expensed

Capitalisation is suspended during extended periods in which active development is interrupted. It is not suspended for temporary delays that are a necessary part of getting the asset ready.