Management & CommerceVery hardCA Inter level
The standard labour rate is ₹30 an hour. Actual hours worked were 2,200. The labour efficiency variance is ₹3,000 adverse and the rate variance ₹2,200 favourable. What were the standard hours for actual output and the actual rate?
- A. 2,300 hours; ₹31
- B. 2,100 hours; ₹31
- C. 2,300 hours; ₹29
- D. 2,100 hours; ₹29
Correct answer: D. 2,100 hours; ₹29
Efficiency: 30 × (SH − 2,200) = −3,000, so SH = 2,100. Rate: 2,200 × (30 − AR) = +2,200, so AR = ₹29. Mixing up the signs gives 2,300 hours or ₹31.
Practise more Financial & Cost Accounting questionsFinancial & Cost Accounting: notes and key points
More Financial & Cost Accounting questions
- 12,000 units are to be produced, each needing 2.5 standard labour hours. Idle time is expected to be 20% of paid hours, and the wage rate…
- Product A makes up 60% of sales value with a P/V ratio of 40%; product B makes up 40% with a P/V ratio of 25%. Fixed costs are ₹3,40,000…
- A joint process costs ₹2,00,000. Its by-product (1,000 kg) sells at ₹30 a kg after packing costs of ₹5 a kg, and selling expenses are 10%…
- Annual demand is 24,000 units, ordering cost ₹150 an order and unit price ₹40. Carrying cost is 15% of price (interest) plus ₹2 a unit a…
- On dissolution, machinery (book value ₹70,000) and other assets (book value ₹2,30,000) go to the realisation account along with creditors…
- At the start of the year taxable temporary differences were ₹4,00,000 with a DTL of ₹1,20,000 at 30%. During the year a further ₹1,00,000…