Overheads: setup cost ₹6,00,000 (driver: number of setups) and machine cost ₹9,00,000 (driver: machine hours). Product P needs 40 of the 60 setups and 3,000 of the 9,000 machine hours, and 10,000 units of P are made. What is the activity-based overhead per unit of P?

  1. A. ₹50
  2. B. ₹40
  3. C. ₹30
  4. D. ₹70

Correct answer: D. ₹70

Setup pool: 600,000 x 40/60 = 400,000; machine pool: 900,000 x 3,000/9,000 = 300,000; total 700,000/10,000 = 70 per unit. Spreading all overhead on machine hours alone gives 50; using only one pool gives 40 or 30.