A construction contract with a fixed price of ₹40 lakh is recognised over time using the cost-to-cost method. At year end, costs incurred are ₹30 lakh and further costs to complete are estimated at ₹20 lakh. What total loss is recognised in profit or loss for the year, including any provision for the onerous contract?
- A. ₹6 lakh
- B. ₹10 lakh
- C. ₹4 lakh
- D. ₹20 lakh
Correct answer: B. ₹10 lakh
Stage of completion = 30/50 = 60%, so revenue = 24 lakh and cost 30 lakh gives a 6 lakh loss to date. The expected total loss of 10 lakh must be recognised at once, so the remaining 4 lakh goes into a provision; total = 10 lakh.
Practise more Financial & Cost Accounting questionsFinancial & Cost Accounting: notes and key points
More Financial & Cost Accounting questions
- A firm's credit sales for January, February and March are ₹2,00,000, ₹3,00,000 and ₹4,00,000. Customers pay 30% in the month of sale…
- Average annual profit of a firm is ₹3,60,000, which includes a non-recurring gain of ₹60,000 and is stated after an abnormal loss of…
- A firm's godown is damaged by fire. Stock at the date of the fire, computed from the trading records, is ₹1,00,000, of which salvage is…
- A and B share profits 3 : 2. C is admitted for a 1/5 share, with a guarantee that his share of profit will not be below ₹1,00,000; A and B…
- An investor buys 30% of an associate for ₹9,00,000. At that date an item of plant in the associate had a fair value ₹4,00,000 above its…
- Land is carried at cost of ₹50 lakh under the revaluation model. It is revalued to ₹80 lakh in year 1, ₹60 lakh in year 2 and ₹35 lakh in…