The first batch of a product takes 100 labour hours. The process follows a 90% cumulative-average learning curve (each doubling of cumulative output cuts the cumulative average time per batch to 90% of its previous value). How many total hours do the first four batches take?

  1. A. 360 hours
  2. B. 291.6 hours
  3. C. 370 hours
  4. D. 324 hours

Correct answer: D. 324 hours

Cumulative average for 2 batches = 90; for 4 batches = 90 x 0.9 = 81; total = 4 x 81 = 324 hours. Applying 90% to every batch (360) or treating each later batch as 90 hours (370) misreads the curve.