Direct materials are ₹50,000, direct labour ₹30,000, direct expenses ₹5,000 and factory overheads ₹20,000. What is the prime cost?

  1. A. ₹80,000
  2. B. ₹85,000
  3. C. ₹1,05,000
  4. D. ₹1,00,000

Correct answer: B. ₹85,000

Prime cost = direct materials + direct labour + direct expenses = ₹85,000. Adding factory overheads gives works cost (₹1,05,000 before WIP adjustment).