Management & CommerceVery hardCA Inter · MBA Placement
A material's standard price was set at ₹50 a kg. A market-wide shortage later makes ₹56 a kg a realistic standard. The buyer actually paid ₹58 a kg for 10,000 kg. What is the operational price variance?
- A. ₹60,000 adverse
- B. ₹20,000 favourable
- C. ₹80,000 adverse
- D. ₹20,000 adverse
Correct answer: D. ₹20,000 adverse
Operational variance compares actual with the revised standard: (56 − 58) × 10,000 = ₹20,000 adverse. The ₹60,000 adverse gap between the original and revised standard is the planning variance, outside the buyer's control.
Practise more Financial & Cost Accounting questionsFinancial & Cost Accounting: notes and key points
More Financial & Cost Accounting questions
- A new product will sell 50,000 units over its life. Life-cycle costs are: R&D ₹40 lakh, design ₹10 lakh, marketing ₹20 lakh…
- Production in April is 12,000 units and in May 15,000 units; each unit needs 3 kg of material at ₹25 a kg. Opening material stock on 1…
- A firm of A and B (profit ratio 3 : 2) is sold to a company for ₹12,00,000: 1,00,000 equity shares of ₹10 issued at ₹11 and the rest in…
- A liquidator is entitled to 2% on assets realised and 3% on amounts paid to unsecured creditors. Assets realise ₹50 lakh. After all prior…
- A loss-of-profit policy has a 6-month indemnity period. Turnover in that period was ₹30 lakh against ₹50 lakh in the same period last…
- A hirer bought a machine on hire purchase for a cash price of ₹4,00,000 and has charged depreciation of ₹1,20,000 to date. He then…