A company using the cost model has a decommissioning provision for a plant. A new estimate raises the provision by ₹2 lakh. How is the increase accounted for under Ind AS 16 and Ind AS 37?

  1. A. Added to the plant's cost and depreciated over its remaining life
  2. B. Charged to profit or loss immediately as an operating expense
  3. C. Debited to the revaluation surplus, or to OCI if there is none
  4. D. Adjusted against opening retained earnings as a prior-period item

Correct answer: A. Added to the plant's cost and depreciated over its remaining life

Under the cost model, changes in the measurement of a decommissioning liability from revised estimates are added to (or deducted from) the related asset's cost and depreciated prospectively; it is a change in estimate, not an error.