Average wages in a factory rise 8% while output per worker rises 5%. By approximately how much does unit labour cost change?

  1. A. 13.00%
  2. B. 2.86%
  3. C. 3.00%
  4. D. −2.78%

Correct answer: B. 2.86%

Unit labour cost = wage/productivity, so it changes by 1.08/1.05 − 1 = 2.86% (≈ 3%). Productivity gains offset most of the wage rise.