On Mendelow's power–interest grid, a stakeholder with high power but low interest in a project (for example, a regulator not directly affected) should usually be:
- A. managed closely as a key player
- B. kept informed with regular updates
- C. monitored with minimal effort
- D. kept satisfied
Correct answer: D. kept satisfied
High power and low interest: keep satisfied so they do not turn against the project. Key players are high on both; 'keep informed' is for high interest but low power; 'monitor' is for low on both.
Practise more Business Economics & Strategy questionsBusiness Economics & Strategy: notes and key points
More Business Economics & Strategy questions
- In Brandenburger and Nalebuff's value net, another firm is your COMPLEMENTOR if:
- A retailer's plan was to grow through company-owned stores, but over three years a franchise model improvised by store managers became its…
- Which is NOT a typical feature of a disruptive innovation in Christensen's sense?
- In the maturity stage of the product life cycle, which marketing focus is most typical?
- Firms in an industry cluster into strategic groups (e.g. premium national brands versus low-cost regional players). What mainly stops…
- The Triffin dilemma describes a conflict faced by the issuer of the world's main reserve currency. What is it?