Management & CommerceModerateMBA Placement · Big 4 Advisory

On Mendelow's power–interest grid, a stakeholder with high power but low interest in a project (for example, a regulator not directly affected) should usually be:

  1. A. managed closely as a key player
  2. B. kept informed with regular updates
  3. C. monitored with minimal effort
  4. D. kept satisfied

Correct answer: D. kept satisfied

High power and low interest: keep satisfied so they do not turn against the project. Key players are high on both; 'keep informed' is for high interest but low power; 'monitor' is for low on both.