A state project has benefits with a present value of ₹50 crore and costs of ₹20 crore for materials and ₹25 crore of wages. The workers would otherwise be unemployed; their shadow wage (opportunity cost) is 40% of the market wage. What is the project's economic NPV?

  1. A. ₹20 crore
  2. B. ₹5 crore
  3. C. ₹30 crore
  4. D. ₹15 crore

Correct answer: A. ₹20 crore

Economic labour cost = 40% × 25 = ₹10 crore, so economic NPV = 50 − 20 − 10 = ₹20 crore. ₹5 crore is the financial NPV at market wages; ₹30 crore treats idle labour as free; ₹15 crore uses 60% instead of 40%.