Management & CommerceHardFinance analyst · Bank MT · MBA placement pattern

A project's NPV is ₹50 lakh in a boom (probability 0.3), ₹20 lakh in a normal year (0.5) and −₹40 lakh in a slump (0.2). What are its expected NPV and coefficient of variation?

  1. A. ₹10 lakh; CV ≈ 3.13
  2. B. ₹17 lakh; CV ≈ 0.54
  3. C. ₹17 lakh; CV ≈ 1.84
  4. D. ₹33 lakh; CV ≈ 0.95

Correct answer: C. ₹17 lakh; CV ≈ 1.84

E(NPV) = 0.3 × 50 + 0.5 × 20 + 0.2 × (−40) = ₹17 lakh. Variance = 0.3(33)² + 0.5(3)² + 0.2(−57)² = 981.0, σ ≈ ₹31.32 lakh. CV = σ/E = 1.84. ₹10 lakh is the simple average of the three scenarios; 0.54 inverts the ratio.