Management & CommerceVery hardMBA finance · Consulting
A ₹100 crore project returns ₹50 crore at the end of year 1. At that point the PV of its remaining cash flows will be either ₹120 crore or ₹30 crore with equal probability. At year 1 the firm may instead abandon it and sell the assets for ₹60 crore. At 10%, what is the value of the abandonment option?
- A. ₹30.00 crore
- B. ₹15.00 crore
- C. ₹13.64 crore
- D. ₹27.27 crore
Correct answer: C. ₹13.64 crore
Abandonment adds ₹30 crore (60 − 30) only in the bad state: 0.5 × 30 = ₹15 crore at year 1, worth 15/1.1 = ₹13.64 crore today. It turns the project NPV from ₹13.64 crore to ₹27.27 crore.
Practise more Corporate Finance & Financial Markets questionsCorporate Finance & Financial Markets: notes and key points
More Corporate Finance & Financial Markets questions
- A ₹20 lakh asset is depreciated straight-line over 4 years to zero. The tax rate is 25% and the discount rate 10%. What is the present…
- Which statements about a conventional project's NPV profile are correct? I. It cuts the horizontal axis at the IRR. II. Its vertical-axis…
- For a new plant, a firm lists: (a) ₹40 lakh already spent on R&D; (b) a building it owns that could be rented out for ₹12 lakh a year; (c)…
- Mutually exclusive projects: A costs ₹1,000 and returns ₹1,200 in a year; B costs ₹10,000 and returns ₹11,000 in a year. The cost of…
- A project's cash flows are ₹100 crore a year for 3 years in TODAY's (real) rupees. The nominal cost of capital is 10.24% and expected…
- A project costs ₹500 lakh and returns ₹200 lakh a year for 4 years. At 12%, what is its equivalent annual annuity (EAA)?