Management & CommerceHardCFA Level I · MBA placement
A project has an NPV of ₹2 crore before financing costs. It needs ₹50 crore of new equity, and issue (flotation) costs are 3% of the amount raised. What is the correct treatment, and the resulting NPV?
- A. Raise the cost of equity for all future projects; NPV stays ₹2 crore
- B. Ignore flotation costs because they are financing flows: NPV = ₹2 crore
- C. Deduct ₹1.5 crore of flotation cost upfront: NPV = ₹0.5 crore
- D. Deduct 3% of NPV: NPV = ₹1.94 crore
Correct answer: C. Deduct ₹1.5 crore of flotation cost upfront: NPV = ₹0.5 crore
The preferred approach treats flotation costs as an actual upfront cash cost of the project (3% × 50 = ₹1.5 crore), giving NPV = ₹0.5 crore, rather than permanently adjusting the cost of capital.
Practise more Corporate Finance & Financial Markets questionsCorporate Finance & Financial Markets: notes and key points
More Corporate Finance & Financial Markets questions
- To value an emerging-market project, an analyst uses a developed-market risk-free rate of 4%, a beta of 1.2 and a mature-market equity…
- A company's 8% preference shares (face ₹100) trade at ₹90, and its bonds yield 9%. Analysts add a 4% risk premium to the bond yield to…
- Under Modigliani–Miller with corporate taxes, an unlevered firm's cost of equity is 12%. A similar firm has a debt–equity ratio of 1, a…
- Continuing with Modigliani–Miller with taxes: Ku = 12%, Kd = 8%, t = 25% and debt is 50% of firm value (D/E = 1). What is the levered…
- Which statements about capital-structure theories are correct? I. The static trade-off theory balances the tax benefit of debt against…
- A firm pays interest of ₹20 lakh and preference dividends of ₹15 lakh a year; the tax rate is 25%. At what EBIT does its EPS become…