A firm's cost of debt is 7% after tax and its WACC is 11%. A project earning an IRR of 9% will be fully financed by a new loan. The manager argues it should be accepted because 9% > 7%. What is the correct view?

  1. A. Accept it, because the specific financing source sets the hurdle
  2. B. Reject if its risk matches the firm's: the hurdle is the 11% WACC
  3. C. Accept it, since its IRR exceeds the after-tax cost of debt of 7%
  4. D. Reject it only if the loan's pre-tax cost exceeds 9%

Correct answer: B. Reject if its risk matches the firm's: the hurdle is the 11% WACC

The hurdle rate depends on the project's risk, not on how it is financed; borrowing for this project reduces capacity for later ones, so using the debt rate alone is wrong.