Which statements about payback are correct? I. Simple payback ignores cash flows after the payback date. II. Discounted payback can never be shorter than simple payback for a conventional project. III. A project with a payback shorter than the cut-off must have a positive NPV.
- A. I, II and III
- B. I only
- C. II and III only
- D. I and II only
Correct answer: D. I and II only
I and II are true. III is false: a project can recover its cost quickly yet have little or nothing after payback, so its NPV can still be negative, especially under simple payback.
Practise more Corporate Finance & Financial Markets questionsCorporate Finance & Financial Markets: notes and key points
More Corporate Finance & Financial Markets questions
- A project costing ₹1,60,000 is expected to generate ₹1,00,000 a year for 2 years in TODAY'S prices. The nominal cost of capital is 15.5%…
- Which capital budgeting method ignores the time value of money?
- A diversified firm uses its company-wide WACC of 11% to evaluate all projects. Over time, this practice tends to:
- Match each technique with its feature. Techniques: (p) NPV, (q) IRR, (r) PI, (s) Payback. Features: (1) Best for ranking divisible…
- The risk-free rate is 6%, the market return is 12% and a stock's beta is 1.2. What is its required return under CAPM?
- A company borrows at 10% and pays tax at 30%. What is its after-tax cost of debt?