Which statements about payback are correct? I. Simple payback ignores cash flows after the payback date. II. Discounted payback can never be shorter than simple payback for a conventional project. III. A project with a payback shorter than the cut-off must have a positive NPV.

  1. A. I, II and III
  2. B. I only
  3. C. II and III only
  4. D. I and II only

Correct answer: D. I and II only

I and II are true. III is false: a project can recover its cost quickly yet have little or nothing after payback, so its NPV can still be negative, especially under simple payback.