Management & CommerceHardMBA Finance · Big 4
A firm can invest ₹50 crore (all values are in present-value terms). With probability 0.6 the project succeeds and its continuing value is ₹120 crore; with probability 0.4 it fails and its continuing value is only ₹20 crore, but the assets could then be sold for ₹40 crore. What is the value of the option to abandon?
- A. ₹8 crore
- B. ₹20 crore
- C. ₹12 crore
- D. ₹16 crore
Correct answer: A. ₹8 crore
The option matters only in the failure state, where it adds 40 - 20 = 20, so its expected value is 0.4 x 20 = 8. Using the full 20 ignores the probability; 0.4 x 40 = 16 counts the salvage as if the project were otherwise worth nothing.
Practise more Corporate Finance & Financial Markets questionsCorporate Finance & Financial Markets: notes and key points
More Corporate Finance & Financial Markets questions
- A project costs ₹100 and returns ₹30 a year for 5 years; the discount rate is 10%. By what percentage can the annual cash flow fall (all…
- A firm needs ₹1 crore and can raise it by issuing 10 lakh equity shares at ₹10 each (it already has 10 lakh shares) or by 10% debentures…
- Acquirer A has 10 crore shares at ₹200; target T has 2 crore shares at ₹80. Synergies are worth ₹50 crore. A offers 0.5 of its own share…
- A bank has an exposure of ₹50 crore to a borrower with a one-year probability of default of 2%. If default occurs, the bank recovers 55%…
- A portfolio worth ₹10 crore has a daily return standard deviation of 1.2%, returns are normal with zero mean, and the one-tailed 99%…
- A scheme pays ₹1,00,000 at the end of the first year, with payments then growing 5% a year, for 10 years in all. At a discount rate of 9%…