A firm can invest ₹50 crore (all values are in present-value terms). With probability 0.6 the project succeeds and its continuing value is ₹120 crore; with probability 0.4 it fails and its continuing value is only ₹20 crore, but the assets could then be sold for ₹40 crore. What is the value of the option to abandon?

  1. A. ₹8 crore
  2. B. ₹20 crore
  3. C. ₹12 crore
  4. D. ₹16 crore

Correct answer: A. ₹8 crore

The option matters only in the failure state, where it adds 40 - 20 = 20, so its expected value is 0.4 x 20 = 8. Using the full 20 ignores the probability; 0.4 x 40 = 16 counts the salvage as if the project were otherwise worth nothing.