Management & CommerceHardCA Intermediate FM · UGC NET Commerce
A project costs ₹100 lakh and is expected to return ₹60 lakh at the end of each of 2 years. Certainty-equivalent coefficients are 0.9 for year 1 and 0.8 for year 2, and the risk-free rate is 6%. What is the NPV?
- A. +₹10.00 lakh
- B. −₹6.66 lakh
- C. +₹2.00 lakh
- D. −₹6.34 lakh
Correct answer: D. −₹6.34 lakh
Certain flows are 54 and 48, discounted at the risk-free rate: 54/1.06 + 48/1.06² − 100 = −₹6.34 lakh. Discounting the uncertain ₹60 lakh at 6% gives +₹10 lakh, double-counting nothing for risk.
Practise more Corporate Finance & Financial Markets questionsCorporate Finance & Financial Markets: notes and key points
More Corporate Finance & Financial Markets questions
- A debt-free company trades at a P/E of 20 and holds idle cash earning 6% before tax (tax rate 25%). It uses part of that cash to buy back…
- 10% preference shares (face ₹100) are issued, net of costs, at ₹95 and will be redeemed at ₹105 after 5 years. Using the approximation…
- A division has EBIT of ₹120 crore, interest of ₹30 crore, a 25% tax rate, invested capital of ₹600 crore and a WACC of 12%. What is its…
- A firm's credit sales are ₹100 lakh on 30-day terms. Extending terms to 60 days would raise sales to ₹120 lakh. Variable cost is 75% of…
- Annual demand is 20,000 units at ₹50 each; ordering cost is ₹400 an order and holding cost 20% of the unit price a year. The supplier…
- A company's annual credit sales are ₹730 crore. Tighter collections cut its days sales outstanding from 50 days to 40 days. If it funds…