Management & CommerceHardCA Inter FM · Operations finance
Daily demand for a part has a standard deviation of 20 units and is independent from day to day. Lead time is 9 days and the firm wants a 95% cycle service level (z = 1.65). What safety stock should it hold?
- A. 33 units
- B. 297 units
- C. 99 units
- D. 180 units
Correct answer: C. 99 units
σ over the lead time = 20 × √9 = 60 units; safety stock = 1.65 × 60 = 99 units. 297 multiplies by 9 days instead of √9, ignoring that independent daily errors partly cancel.
Practise more Corporate Finance & Financial Markets questionsCorporate Finance & Financial Markets: notes and key points
More Corporate Finance & Financial Markets questions
- An online retailer holds inventory for 20 days, collects from customers in 5 days and pays suppliers in 60 days. What is its cash…
- Using the adjustment for shareholders' alternatives, shareholders' required return is 15%, their tax rate on dividends is 30% and…
- A firm sells 10,000 units with a contribution of ₹30 a unit and fixed costs of ₹2,90,000. What is its degree of operating leverage, and…
- Jensen's free-cash-flow hypothesis predicts that:
- A company earns net profit of ₹100 crore and has 50 crore shares. It has ₹200 crore of 9% convertible bonds, convertible into 10 crore…
- A VC invested ₹10 crore for 25% of a start-up with a 1× non-participating liquidation preference. The start-up is sold for ₹30 crore. How…