A new project will use a machine's spare capacity. Without the project, the firm would need to buy a new ₹100 lakh machine in 4 years; with it, the purchase moves to 2 years from now. At 10%, what cost should be charged to the project for the spare capacity?
- A. Nothing, as the capacity is idle
- B. ₹82.64 lakh
- C. ₹68.30 lakh
- D. ₹14.34 lakh
Correct answer: D. ₹14.34 lakh
The incremental cost is bringing the purchase forward: 100/1.1² − 100/1.1⁴ = 82.64 − 68.30 = ₹14.34 lakh. Idle today does not mean free; charging the whole ₹82.64 lakh ignores the purchase that would have happened anyway.
Practise more Corporate Finance & Financial Markets questionsCorporate Finance & Financial Markets: notes and key points
More Corporate Finance & Financial Markets questions
- Compare a 10-year amortising loan (equal annual instalments) with a 10-year bullet bond at the same yield and coupon rate. Which statement…
- A conglomerate wants to raise cash while keeping control of a subsidiary. Which route fits?
- Annual demand for an item rises by 44% while ordering cost per order and holding cost per unit stay the same. By how much do the EOQ and…
- A firm's value with debt D (₹ crore) is V = 500 + 0.25D − 0.001D², the tax shield net of expected distress costs. What debt level…
- A ₹10 lakh loan at 12% a year (1% a month) is repaid by 36 equal monthly instalments plus a balloon of ₹3 lakh paid with the last…
- A 3-year bond of face value ₹1,000 pays an 8% annual coupon and its yield to maturity is 10%, so its price is ₹950.26 and its Macaulay…