Management & CommerceVery hardUGC NET Management

A project returns ₹100 a year for 3 years in real (constant-price) terms. The nominal cost of capital is 15.5% and inflation is 5%. The project's present value is closest to

  1. A. ₹226.4
  2. B. ₹248.7
  3. C. ₹272.9
  4. D. ₹300.0

Correct answer: B. ₹248.7

Real rate = 1.155/1.05 − 1 = 10%. PV of real flows at 10% = 100 × 2.4869 = ₹248.7. Discounting real flows at the nominal rate gives ₹226.4, a mismatch.