A plant's gainsharing plan sets a baseline labour cost of 25% of the value of production and shares 50% of any savings equally among its 200 employees. This month production is worth ₹80 lakh and actual labour cost is ₹18 lakh. How much does each employee receive?

  1. A. ₹1,000
  2. B. ₹750
  3. C. ₹250
  4. D. ₹500

Correct answer: D. ₹500

Allowed labour cost = 25% × ₹80 lakh = ₹20 lakh. Savings = ₹2 lakh; the employees' half = ₹1 lakh; shared among 200 = ₹500 each. ₹1,000 forgets that only half the savings are shared.