A project team with a 12-week deadline drifts with little progress for about six weeks, then suddenly drops its old approach, adopts a new plan and works intensely until the end. Which model of group development describes this?
- A. Tuckman's forming–storming model
- B. Punctuated-equilibrium model
- C. Lewin's three-step change model
- D. Belbin's team-role model
Correct answer: B. Punctuated-equilibrium model
Gersick's punctuated-equilibrium model: temporary groups with deadlines show inertia until about the midpoint, then a burst of change, a second phase of inertia and a final push. Tuckman's stages describe a steady sequence, not a midpoint jolt.
Practise more HR, Organisational Behaviour & Principles of Management questionsHR, Organisational Behaviour & Principles of Management: notes and key points
More HR, Organisational Behaviour & Principles of Management questions
- A work group is very close-knit, but its informal norm is to do the bare minimum. Compared with other combinations of cohesiveness and…
- Before a meeting, each member of an investment committee privately favours a moderately risky investment. After discussion, the committee…
- In a product team, one member generates highly original but sometimes impractical ideas, another coolly weighs all options and judges them…
- A team member is outgoing, has a wide network outside the company, and keeps bringing back contacts and ideas from other firms, though she…
- Cyclists ride faster when racing alongside others, and skilled typists type faster when watched, but trainees solving unfamiliar complex…
- Alone, each of three workers can pull a load of 60 kg, 65 kg and 64 kg. Pulling together, the three manage only 160 kg. What is the…