A manager keeps pouring money into a failing software project, arguing that "we have already spent ₹2 crore — we can't stop now." This is:

  1. A. Escalation of commitment (sunk-cost trap)
  2. B. Anchoring bias (fixating on the ₹2 crore)
  3. C. Availability bias (vivid recent failures)
  4. D. Confirmation bias (seeking agreeing data)

Correct answer: A. Escalation of commitment (sunk-cost trap)

Escalation of commitment is sticking with a losing course because of past investment. Sunk costs should be ignored; only future costs and benefits matter.