Management & CommerceHardHR analyst · Consulting · MBA placement pattern
A manager keeps pouring money into a failing software project, arguing that "we have already spent ₹2 crore — we can't stop now." This is:
- A. Escalation of commitment (sunk-cost trap)
- B. Anchoring bias (fixating on the ₹2 crore)
- C. Availability bias (vivid recent failures)
- D. Confirmation bias (seeking agreeing data)
Correct answer: A. Escalation of commitment (sunk-cost trap)
Escalation of commitment is sticking with a losing course because of past investment. Sunk costs should be ignored; only future costs and benefits matter.
Practise more HR, Organisational Behaviour & Principles of Management questionsHR, Organisational Behaviour & Principles of Management: notes and key points
More HR, Organisational Behaviour & Principles of Management questions
- In a salary negotiation, the candidate opens with a high figure, and the final offer ends up much higher than the employer originally…
- Consider these statements about the matrix structure: I. Dual reporting can create role ambiguity and conflict. II. It allows specialist…
- A firm can launch a product itself (60% chance of ₹50 lakh profit, 40% chance of a ₹20 lakh loss) or license it for a guaranteed ₹18 lakh…
- For the same choice (launch: 60% chance of +₹50 lakh, 40% chance of −₹20 lakh; license: certain ₹18 lakh), what is the expected value of…
- Assertion (A): A retail chain operating in very different regional markets often lets regional heads decide pricing and product range…
- A sportswear company designs products and manages its brand in-house but outsources manufacturing, logistics and customer support to…