A company's projects keep finishing late, even though its planners have years of data showing similar projects took 40% longer than planned. Each new plan still assumes things will go smoothly. Which bias is this, and what is a good remedy?
- A. Anchoring; stop using any past data in the planning process
- B. Escalation of commitment; cancel all the delayed projects at once
- C. Hindsight bias; review plans only after each project is complete
- D. Planning fallacy; forecast from a reference class of past projects
Correct answer: D. Planning fallacy; forecast from a reference class of past projects
The planning fallacy is underestimating time and cost despite knowing that past efforts overran. Reference-class forecasting corrects it by anchoring estimates on the actual outcomes of similar projects.
Practise more HR, Organisational Behaviour & Principles of Management questionsHR, Organisational Behaviour & Principles of Management: notes and key points
More HR, Organisational Behaviour & Principles of Management questions
- Galbraith's information-processing view says that as task uncertainty rises, an organisation must either reduce its need to process…
- Herbert Simon described decision making as three phases. Which order is correct?
- A training manager uses an 80% learning curve: each time cumulative output doubles, the time per unit falls to 80% of its previous level…
- A manager meets her best performers individually to ask what keeps them in the company, what might tempt them away and what would make…
- Assertion (A): A firm that copies the 'best practices' of a successful rival exactly may still see poor results. Reason (R): The best-fit…
- A sales team's incentive pays the top 10% of reps a large bonus. Most reps believe that winners are decided mainly by which territory they…