A company's projects keep finishing late, even though its planners have years of data showing similar projects took 40% longer than planned. Each new plan still assumes things will go smoothly. Which bias is this, and what is a good remedy?

  1. A. Anchoring; stop using any past data in the planning process
  2. B. Escalation of commitment; cancel all the delayed projects at once
  3. C. Hindsight bias; review plans only after each project is complete
  4. D. Planning fallacy; forecast from a reference class of past projects

Correct answer: D. Planning fallacy; forecast from a reference class of past projects

The planning fallacy is underestimating time and cost despite knowing that past efforts overran. Reference-class forecasting corrects it by anchoring estimates on the actual outcomes of similar projects.