Management & CommerceHardHR analyst · operations · MBA placement
A plant needs 2,000 extra labour hours next year. Overtime is paid at double the ordinary rate of ₹200 an hour and attracts no extra benefits. Alternatively it can hire one worker for exactly 2,000 hours at ₹200 an hour, with benefits costing 40% of wages and one-time hiring and training costs of ₹1,00,000. By how much is hiring cheaper for the year?
- A. ₹2,40,000
- B. ₹1,40,000
- C. ₹4,00,000
- D. ₹4,60,000
Correct answer: B. ₹1,40,000
Overtime = 2,000 × ₹400 = ₹8,00,000. Hiring = 2,000 × ₹200 × 1.4 + ₹1,00,000 = ₹6,60,000, so hiring saves ₹1,40,000. Forgetting the hiring cost gives ₹2,40,000, ignoring benefits too gives ₹4,00,000, and loading benefits onto the overtime gives ₹4,60,000.
Practise more HR, Organisational Behaviour & Principles of Management questionsHR, Organisational Behaviour & Principles of Management: notes and key points
More HR, Organisational Behaviour & Principles of Management questions
- Two assessors independently mark 50 group-discussion candidates as Pass or Fail. Both say Pass for 20, both say Fail for 15, A passes and…
- A sales rep earns 5% commission with a recoverable draw of ₹30,000 a month: each month she is paid the higher of the draw and (commission…
- In a promotion cycle, Department A promoted 48 of 80 men and 13 of 20 women; Department B promoted 4 of 20 men and 20 of 80 women…
- A firm of 400 staff has 20% annual attrition and a replacement cost of ₹3 lakh per leaver. A ₹40 lakh retention programme is expected to…
- Assume this rule for registering a trade union of workmen: at least 7 members, and also not less than 10% of the workmen in the…
- Under India's Employees' Compensation Act, an employer is generally liable for personal injury caused by an accident arising out of and in…