Management & CommerceEasyMBA Placement · Principles of Management

Which tool, devised by Henry Gantt, shows planned and actual progress of each task as horizontal bars against a time scale?

  1. A. PERT network
  2. B. Pareto chart
  3. C. Gantt chart
  4. D. Fishbone diagram

Correct answer: C. Gantt chart

The Gantt chart plots tasks as bars on a calendar so managers can compare schedule with progress. PERT is a network of events with time estimates, a Pareto chart ranks causes and a fishbone diagram maps causes of a problem.