Management & CommerceHardMBA Placement · Labour Law

A unionised factory covered by India's Industrial Disputes Act wants to change its shift timings and weekly rest days, matters listed in the Fourth Schedule. What must it do before the change takes effect?

  1. A. Obtain prior permission from the appropriate government for the change
  2. B. Give the affected workmen at least 21 days' notice of the change
  3. C. Hold a secret ballot of workers and win a majority vote
  4. D. Give 60 days' notice, the same as is needed for a strike

Correct answer: B. Give the affected workmen at least 21 days' notice of the change

Section 9A requires at least 21 days' notice to affected workmen before changing Fourth Schedule conditions of service such as shifts, hours and rest days (the Industrial Relations Code keeps a 21-day notice). Government permission is needed for lay-off, retrenchment and closure in larger units, not for this.

More HR, Organisational Behaviour & Principles of Management questions