Management & CommerceVery hardUGC NET Management
Design and production departments at a company pass work back and forth repeatedly in a cycle, each modifying its output on the other's feedback. According to Thompson, this interdependence and the best coordination are
- A. sequential; schedules and plans
- B. pooled; rules and standardisation
- C. reciprocal; mutual adjustment
- D. reciprocal; standardised rules
Correct answer: C. reciprocal; mutual adjustment
Work flowing back and forth in both directions is reciprocal interdependence, which is the most demanding and is coordinated by mutual adjustment (liaison, cross-functional teams).
Practise more HR, Organisational Behaviour & Principles of Management questionsHR, Organisational Behaviour & Principles of Management: notes and key points
More HR, Organisational Behaviour & Principles of Management questions
- In a point-factor job evaluation, the maximum is 1,000 points, with factor weights of skill 60%, effort 25% and responsibility 15%. A job…
- An employee thinks that effort leads to good performance with probability 0.8. Good performance leads to a bonus (instrumentality 0.5…
- Which of these is NOT one of the core functions of management in the POSDC framework?
- A machine operator gets conflicting instructions from both the production manager and the quality manager every day. Which of Fayol's…
- A factory engineer times each worker's movements with a stopwatch to find the single best way of doing every task and then trains all…
- Two supervisors at the same level in different departments need to coordinate urgently. With their managers' permission, they talk…