Management & CommerceVery hardMBA Placement · Product Management
A project needs ₹6 crore of development now. Development succeeds technically with probability 0.8; only if it does will the firm spend ₹10 crore on launch, and the launch then succeeds commercially with probability 0.5, giving earnings with a present value of ₹50 crore (zero if it fails). What is the project's expected commercial value today?
- A. ₹4 crore
- B. ₹10 crore
- C. ₹12 crore
- D. ₹6 crore
Correct answer: D. ₹6 crore
ECV = 0.8 × (0.5 × 50 − 10) − 6 = 0.8 × 15 − 6 = ₹6 crore. Treating the launch cost as certain gives ₹4 crore, applying both probabilities to (50 − 10) gives ₹10 crore and leaving out development cost gives ₹12 crore.
Practise more Marketing & Sales Management questionsMarketing & Sales Management: notes and key points
More Marketing & Sales Management questions
- A subscription service adds 1,000 new subscribers a month and loses 4% of its subscriber base each month. If both rates stay constant, at…
- A support desk has one agent who serves 10 customers an hour; arrivals are random (Poisson) and service times exponential. Arrivals are 8…
- Out of 1,000 supermarket baskets, 200 contain bread, 100 contain butter and 60 contain both. What is the lift of the association rule…
- A 200 g pack of tea sells for ₹90 and a 500 g pack of the same tea for ₹240. Compared per gram, the larger pack is:
- Two electronics chains in a city both advertise: 'Find a lower price at a rival and we will match it.' What does game theory suggest is…
- A software vendor's contracts promise each large client that if it ever gives another client a lower price, the client will get that price…