A project needs ₹6 crore of development now. Development succeeds technically with probability 0.8; only if it does will the firm spend ₹10 crore on launch, and the launch then succeeds commercially with probability 0.5, giving earnings with a present value of ₹50 crore (zero if it fails). What is the project's expected commercial value today?

  1. A. ₹4 crore
  2. B. ₹10 crore
  3. C. ₹12 crore
  4. D. ₹6 crore

Correct answer: D. ₹6 crore

ECV = 0.8 × (0.5 × 50 − 10) − 6 = 0.8 × 15 − 6 = ₹6 crore. Treating the launch cost as certain gives ₹4 crore, applying both probabilities to (50 − 10) gives ₹10 crore and leaving out development cost gives ₹12 crore.