Four salespersons P, Q, R, S are to be assigned one each to territories T1–T4. Expected monthly sales (₹ lakh), columns T1–T4: P: 38, 40, 28, 33; Q: 31, 37, 35, 26; R: 42, 34, 30, 29; S: 27, 32, 36, 30. What is the maximum total sales?
- A. ₹144 lakh
- B. ₹155 lakh
- C. ₹135 lakh
- D. ₹148 lakh
Correct answer: D. ₹148 lakh
Best assignment: P→T4, Q→T2, R→T1, S→T3 = 148. Grabbing the largest cell each time (R→T1 42, P→T2 40, then S→T3 36, Q→T4 26) gives 144; adding each row's maximum (155) is not a valid assignment. For the Hungarian method, first convert to a loss matrix by subtracting every entry from 42.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- When the Hungarian method is used for a maximisation assignment problem, what is the first step?
- Assertion (A): The assignment problem is a special case of the transportation problem. Reason (R): In an assignment problem every supply…
- A firm must choose a plant size. Payoffs (₹ lakh) under low, medium and high demand: Small 40, 45, 50; Medium 20, 60, 80; Large −30, 50…
- A firm must choose a plant size. Payoffs (₹ lakh) under low, medium and high demand: Small 40, 45, 50; Medium 20, 60, 80; Large −30, 50…
- A firm must choose a plant size. Payoffs (₹ lakh) under low, medium and high demand: Small 40, 45, 50; Medium 20, 60, 80; Large −30, 50…
- A firm must choose a plant size. Payoffs (₹ lakh) under low, medium and high demand: Small 40, 45, 50; Medium 20, 60, 80; Large −30, 50…