Management & CommerceVery hardOps MT · Supply chain · MBA placement pattern
A bottleneck machine has 2,400 minutes a month. Product X earns a contribution of ₹60 and needs 6 bottleneck minutes; Y earns ₹40 and needs 3 minutes; Z earns ₹90 and needs 10 minutes. Monthly demand is 200 X, 300 Y and 150 Z. What is the maximum monthly contribution?
- A. ₹26,700
- B. ₹37,500
- C. ₹22,500
- D. ₹24,000
Correct answer: A. ₹26,700
Rank by contribution per bottleneck minute: Y 40/3 = 13.33, X 60/6 = 10, Z 90/10 = 9. Make all 300 Y (900 min) and all 200 X (1,200 min); the remaining 300 min make 30 Z. Contribution = 12,000 + 12,000 + 2,700 = ₹26,700. Ranking by contribution per unit (Z first) gives only ₹22,500; ₹37,500 ignores the capacity limit.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- An e-commerce firm receives 600 returns a day, and each pending return carries an average refund of ₹1,500 owed to the customer. A return…
- A buyer scores three vendors out of 10 on cost (weight 40%), quality (35%) and delivery (25%). V1: 8, 6, 9. V2: 6, 9, 7. V3: 7, 8, 8…
- Which supply-chain metric is calculated as 365 ÷ annual inventory turnover?
- A firm has days inventory outstanding of 45, days sales outstanding of 30 and days payables outstanding of 50. If it cuts inventory by 5…
- A firm compares two plant sites on four factors with weights: labour cost 0.30, proximity to market 0.25, infrastructure 0.25 and tax…
- A distributor ships 300 tonnes a year to market A at grid point (20, 40), 500 tonnes to market B at (60, 10) and 200 tonnes to market C at…