Management & CommerceVery hardOps MT · Supply chain · MBA placement pattern

An item is ordered 500 units at a time. Lead-time demand is normal with σ = 40 units, and the firm holds safety stock of 40 units (z = 1). For z = 1, the cumulative normal probability is 0.8413 and the standard loss function L(z) = 0.0833. What are the cycle-service level and the fill rate?

  1. A. CSL 99.3%; fill rate 84.1%
  2. B. CSL 84.1%; fill rate 84.1%
  3. C. CSL 84.1%; fill rate 99.3%
  4. D. CSL 84.1%; fill rate 91.7%

Correct answer: C. CSL 84.1%; fill rate 99.3%

CSL = P(lead-time demand ≤ ROP) = 84.1%. Expected shortage per cycle = L(z) × σ = 0.0833 × 40 ≈ 3.33 units. Fill rate = 1 − 3.33 ÷ 500 ≈ 99.3%. 91.7% wrongly uses 1 − L(z). A modest CSL can still give a very high fill rate when the order quantity is large.