Management & CommerceHardBusiness analyst · KPO · MBA placement pattern
1 December 2026 is a Tuesday. A project tracker computes =NETWORKDAYS(DATE(2026,12,1), DATE(2026,12,31), DATE(2026,12,25)), with 25 December as the only holiday. What does it return?
- A. 23
- B. 30
- C. 21
- D. 22
Correct answer: D. 22
NETWORKDAYS counts Monday–Friday dates, including both end dates, and drops listed holidays that fall on weekdays. December 2026 has 23 weekdays (it starts on a Tuesday and ends on a Thursday). 25 December 2026 is a Friday, so 23 − 1 = 22. 23 ignores the holiday; 30 is DATEDIF-style day counting.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A planner needs to pack 1,250 units into cartons of 48. What does =ROUNDUP(1250/48, 0) + ROUND(1250/48, 0) + ROUNDDOWN(-1250/48, 0) return?
- B2:B7 hold 45, 80, 62, 80, 30 and 55. What does =RANK(B5, B2:B7) + RANK(B4, B2:B7) + RANK(B4, B2:B7, 1) return?
- An analyst models a ₹5,00,000 equipment loan at 10% a year, repaid monthly over 3 years, using =PMT(10%/12, 36, -500000). What monthly…
- An app's dashboard shows average daily active users of 30,000 and monthly active users of 1,20,000. What is its DAU/MAU 'stickiness' ratio?
- Table empsales(rep, region, amount) has 8 rows: (Asha, North, 500), (Ravi, North, 700), (Meena, North, 700), (Kiran, North, 300), (Dev…
- Table empsales(rep, region, amount) has 8 rows: (Asha, North, 500), (Ravi, North, 700), (Meena, North, 700), (Kiran, North, 300), (Dev…