1 December 2026 is a Tuesday. A project tracker computes =NETWORKDAYS(DATE(2026,12,1), DATE(2026,12,31), DATE(2026,12,25)), with 25 December as the only holiday. What does it return?

  1. A. 23
  2. B. 30
  3. C. 21
  4. D. 22

Correct answer: D. 22

NETWORKDAYS counts Monday–Friday dates, including both end dates, and drops listed holidays that fall on weekdays. December 2026 has 23 weekdays (it starts on a Tuesday and ends on a Thursday). 25 December 2026 is a Friday, so 23 − 1 = 22. 23 ignores the holiday; 30 is DATEDIF-style day counting.