Maximise Z = 5x + 4y subject to 6x + 4y ≤ 24 (machine hours), x + 2y ≤ 6 (labour hours), x, y ≥ 0. The optimum is Z = 21. What is the shadow price of one extra machine hour?

  1. A. ₹0.75
  2. B. ₹0.5
  3. C. ₹0.83
  4. D. ₹0

Correct answer: A. ₹0.75

Both constraints bind at x = 3, y = 1.5. Raising machine hours to 25 moves the corner to x = 3.25, y = 1.375, giving Z = 21.75, so the shadow price is 0.75. ₹0.50 is the labour-hour shadow price; ₹0 would apply only to a slack constraint.