Assembly tasks (time in seconds; immediate predecessors): A 5 (–), B 3 (A), C 4 (A), D 6 (B), E 2 (C), F 5 (D, E). Using the ranked positional weight method, what is the positional weight of task C?

  1. A. 6 seconds
  2. B. 9 seconds
  3. C. 25 seconds
  4. D. 11 seconds

Correct answer: D. 11 seconds

A task's positional weight is its own time plus the times of all tasks that follow it: C (4) + E (2) + F (5) = 11. Counting only the immediate successor gives 6; 25 is A's weight, since every task follows A.