Maximise Z = 4x + 3y subject to 2x + y ≤ 20, x + 3y ≤ 30, x ≤ 8, x, y ≥ 0. What is the optimal value of Z, and which constraint is not binding at the optimum?

  1. A. Z = 44; x + 3y ≤ 30 has a slack of 10
  2. B. Z = 48; x ≤ 8 has a slack of 2
  3. C. Z = 48; 2x + y ≤ 20 has a slack of 2
  4. D. Z = 40; x ≤ 8 has a slack of 0

Correct answer: B. Z = 48; x ≤ 8 has a slack of 2

Corners: (0,0) 0, (8,0) 32, (8,4) 44, (6,8) 48, (0,10) 30. The optimum is (6,8), where 2x + y = 20 and x + 3y = 30 both bind, while x = 6 leaves 2 units of slack in x ≤ 8. Stopping at (8,4) gives 44.