Four jobs J1–J4 are to be assigned one each to machines M1–M4. Costs (₹ hundred), rows J1–J4, columns M1–M4: J1: 14, 5, 8, 7; J2: 2, 12, 6, 5; J3: 7, 8, 3, 9; J4: 2, 4, 6, 10. What is the minimum total cost?
- A. ₹15 hundred
- B. ₹12 hundred
- C. ₹17 hundred
- D. ₹14 hundred
Correct answer: A. ₹15 hundred
Optimal: J1→M2 (5), J2→M4 (5), J3→M3 (3), J4→M1 (2) = 15. Picking each row's minimum (5 + 2 + 3 + 2 = 12) is infeasible because J2 and J4 both want M1; the Hungarian method resolves this clash at a cost of 15.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- In an assignment problem, worker W3 is not allowed to operate machine M2 for safety reasons. How is this handled in the Hungarian method…
- In a two-person zero-sum game, the row player's payoffs are: R1: 4, 2, 5; R2: 6, 3, 7; R3: 1, 0, 8 (columns C1–C3). What is the value of…
- A two-person zero-sum game has the row player's payoff matrix R1: 5, 1; R2: 2, 4 (columns C1, C2). What is the value of the game?
- A firm can spend ₹20 lakh on R&D that succeeds with probability 0.6 (failure is worth nothing). If it succeeds, the firm can either…
- A machine produces 5% defective parts, independently. In a box of 10 parts, what is the probability of finding at least 2 defectives?
- Urgent tickets reach an IT team at an average of 2 per hour (Poisson). What is the probability of 3 or more urgent tickets in a given hour?