Management & CommerceVery hardBusiness analyst · KPO · MBA placement pattern

Forecast errors (actual − forecast) for six months were +5, +8, −3, +7, +6 and +9. Control limits for the tracking signal are ±4. What is the tracking signal and what does it say?

  1. A. 5.05; the method consistently under-forecasts
  2. B. 0.84; average error is small next to MAD, so in control
  3. C. 32; the cumulative error itself breaches the +4 limit
  4. D. 5.05; the method consistently over-forecasts demand

Correct answer: A. 5.05; the method consistently under-forecasts

Running sum of errors = 32; MAD = 38/6 = 6.333. TS = 32 ÷ 6.333 = 5.05, beyond +4. Positive errors mean actual > forecast, so the method under-forecasts.