For an outlay of ₹1,000 now followed by inflows of ₹400 at the end of each of the next three years, at 10%, an analyst wrongly enters =NPV(10%, -1000, 400, 400, 400). Approximately what does Excel show, compared with the true NPV?

  1. A. About -4.78 instead of about -5.26
  2. B. About -5.26 – the same as the true NPV
  3. C. About -5.79 instead of about -5.26
  4. D. About 200.00 instead of about -5.26

Correct answer: A. About -4.78 instead of about -5.26

NPV treats −1,000 as a cash flow at the end of year 1 and the inflows at years 2–4, giving -4.78. The correct NPV, with the outlay undiscounted, is -5.26. The mistake shifts every cash flow one period later.