Seven jobs taking 8, 7, 6, 5, 4, 3 and 2 hours are to be run on three identical parallel machines. Using the longest-processing-time (LPT) rule – assign each job, longest first, to the machine that is free earliest – what makespan results, and is it optimal?

  1. A. 13 hours; not optimal, since 12 hours is achievable
  2. B. 12 hours; optimal
  3. C. 13 hours; optimal, since LPT is always optimal
  4. D. 11.67 hours; optimal, as it splits the 35 hours equally

Correct answer: A. 13 hours; not optimal, since 12 hours is achievable

LPT loads: 8+3+2 = 13, 7+4 = 11, 6+5 = 11, so the makespan is 13. But {8, 4}, {7, 5}, {6, 3, 2} gives 12, 12, 11 – a 12-hour schedule. LPT is a good heuristic, not a guarantee; 11.67 (35/3) is only a lower bound.