Management & CommerceVery hardOps MT · MBA placement
Seven jobs taking 8, 7, 6, 5, 4, 3 and 2 hours are to be run on three identical parallel machines. Using the longest-processing-time (LPT) rule – assign each job, longest first, to the machine that is free earliest – what makespan results, and is it optimal?
- A. 13 hours; not optimal, since 12 hours is achievable
- B. 12 hours; optimal
- C. 13 hours; optimal, since LPT is always optimal
- D. 11.67 hours; optimal, as it splits the 35 hours equally
Correct answer: A. 13 hours; not optimal, since 12 hours is achievable
LPT loads: 8+3+2 = 13, 7+4 = 11, 6+5 = 11, so the makespan is 13. But {8, 4}, {7, 5}, {6, 3, 2} gives 12, 12, 11 – a 12-hour schedule. LPT is a good heuristic, not a guarantee; 11.67 (35/3) is only a lower bound.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A machine has a mean time between failures of 400 hours and a mean time to repair of 20 hours. What is its steady-state availability?
- A pump fails at random (constant failure rate) with a mean time between failures of 400 hours. What is the probability that it runs a…
- A subscriber yields a margin of ₹600 a year, paid at the end of each year he stays. The annual retention rate is 80% and the discount rate…
- Acquiring a customer costs ₹3,000. Each customer pays ₹500 a month at a 60% gross margin and is retained throughout. Ignoring discounting…
- When a product's price rose from ₹100 to ₹120, monthly sales fell from 1,000 to 850 units. What is the arc (midpoint) price elasticity of…
- Three SKUs have actual sales of 10, 100 and 1,000 units and forecasts of 20, 90 and 1,010. Which statement about the accuracy metrics is…