In acceptance sampling, a good lot (at the acceptable quality level) is rejected by the sampling plan. What kind of error is this, and who bears its risk?

  1. A. Type II error – the consumer's risk (β)
  2. B. Type I error – the producer's risk (α)
  3. C. Type I error – the consumer's risk (β)
  4. D. Type II error – the producer's risk (α)

Correct answer: B. Type I error – the producer's risk (α)

Rejecting a lot that should be accepted is a Type I error; its probability α is called the producer's risk because the producer loses a good lot. Accepting a bad lot (at the LTPD) is a Type II error, the consumer's risk β.