Management & CommerceVery hardOps MT · MBA placement

The first unit of a new product takes 100 labour hours, and labour follows an 80% unit learning curve (Tₙ = T₁ × n^b, b = log 0.8/log 2 ≈ −0.322). About how many hours will the first four units take in total?

  1. A. About 256 hours
  2. B. About 314 hours
  3. C. 400 hours
  4. D. About 344 hours

Correct answer: B. About 314 hours

T₂ = 80, T₃ = 100 × 3^(−0.322) ≈ 70.2, T₄ = 64. Total ≈ 100 + 80 + 70.2 + 64 ≈ 314. 256 = 4 × 64 uses the 4th unit's time for every unit; 400 ignores learning.