Average daily demand is 50 units with a standard deviation of 8 units per day; the lead time is a constant 9 days. For a 95% cycle-service level (z = 1.65), what is the reorder point?

  1. A. 463.2 units
  2. B. 489.6 units
  3. C. 450.0 units
  4. D. 568.8 units

Correct answer: B. 489.6 units

σ over lead time = 8 × √9 = 24. Safety stock = 1.65 × 24 = 39.6. ROP = 50 × 9 + 39.6 = 489.6. Multiplying σ by 9 instead of √9 gives 568.8.