Average daily demand is 50 units with a standard deviation of 8 units per day; the lead time is a constant 9 days. For a 95% cycle-service level (z = 1.65), what is the reorder point?
- A. 463.2 units
- B. 489.6 units
- C. 450.0 units
- D. 568.8 units
Correct answer: B. 489.6 units
σ over lead time = 8 × √9 = 24. Safety stock = 1.65 × 24 = 39.6. ROP = 50 × 9 + 39.6 = 489.6. Multiplying σ by 9 instead of √9 gives 568.8.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Daily demand averages 100 units (σ = 20 units/day). Lead time averages 4 days (σ = 1 day); demand and lead time are independent. For z =…
- Annual usage and unit cost of six items: P 500 units at ₹400; Q 10,000 at ₹2; R 2,000 at ₹50; S 50 at ₹600; T 8,000 at ₹5; U 1,000 at ₹10…
- Match each inventory classification with its basis. 1. ABC 2. VED 3. FSN 4. HML a. Rate of movement (issues) b. Criticality to operations…
- Which of the following cause the bullwhip effect in a supply chain? I. Each tier updating its forecast from the orders it receives II…
- Assertion (A): Vendor-managed inventory (VMI) tends to dampen the bullwhip effect. Reason (R): Under VMI the supplier sees the retailer's…
- A firm makes a part in-house. Annual demand is 18,000 units (300 working days, so 60 units/day). The production rate is 100 units/day…