A supplier's lead time is uniformly distributed between 4 and 10 days. What is the probability that a given order takes more than 8 days to arrive?

  1. A. 20%
  2. B. 80%
  3. C. About 33%
  4. D. About 67%

Correct answer: C. About 33%

For a uniform distribution on [4, 10], P(L > 8) = (10 − 8)/(10 − 4) = 2/6 ≈ 33%. Dividing by 10 (as if it started at 0) gives 20%.