Forecast errors are defined as actual − forecast. Over 12 months the mean forecast error is +35 units and the tracking signal is +5.2. What does this indicate?

  1. A. The forecast is biased high: it is consistently over-forecasting demand
  2. B. The forecast is biased low: it is consistently under-forecasting
  3. C. The forecast is unbiased because positive and negative errors cancel
  4. D. The forecast has high random error but no bias, as the TS shows

Correct answer: B. The forecast is biased low: it is consistently under-forecasting

A positive mean error with actual − forecast means actuals usually exceed forecasts – under-forecasting. A tracking signal of +5.2 (outside typical ±4 limits) confirms a persistent bias rather than random noise.