Management & CommerceHardBusiness analyst · MBA placement

Two independent risks hit a project: a supplier delay with probability 0.4 and a design change with probability 0.3. What is the probability that at least one occurs?

  1. A. 0.70
  2. B. 0.12
  3. C. 0.42
  4. D. 0.58

Correct answer: D. 0.58

P(A or B) = P(A) + P(B) − P(A)P(B) = 0.4 + 0.3 − 0.12 = 0.58. Adding (0.70) double-counts the overlap; 0.12 is both together; 0.42 is neither (0.6 × 0.7).