Management & CommerceHardOps MT · MBA placement
Simple exponential smoothing is run with α = 1. What does the forecast for next period equal?
- A. This period's forecast, carried forward unchanged
- B. The average of all past demand, equally weighted
- C. Zero, because no smoothing occurs when α = 1
- D. This period's actual demand (the naive forecast)
Correct answer: D. This period's actual demand (the naive forecast)
Fₜ₊₁ = αAₜ + (1 − α)Fₜ. With α = 1 the old forecast gets no weight, so the forecast is the latest actual – the naive method. With α = 0 the forecast would never change.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- An analyst fits a 12-variable regression to 30 months of sales and gets R² = 0.97 on that data, but forecasts for the next 6 months are…
- A process has specification width 12 mm and standard deviation 2 mm. An improvement cuts the standard deviation to 1.5 mm. What happens to…
- A process's specification limits are exactly ±3σ from the target, and it was centred. Its mean then shifts by 1σ (σ unchanged)…
- In a cost-minimising diet LP, the protein constraint (at least 50 g) is binding with a shadow price of ₹3 per gram. What happens if the…
- A feed is blended from ingredient X (30% protein) and ingredient Y (10% protein), in kg amounts x and y. The blend must be at least 20%…
- Payoffs (₹ lakh): act A gives 40 if demand is high (probability 0.6) and 10 if low; act B gives 20 if high and 30 if low. What is the…