Management & CommerceHardOps MT · Supply chain · MBA placement pattern
The standard deviation of lead-time demand is 50 units and holding cost is ₹10 per unit per year. Raising the cycle-service level from 95% (z = 1.645) to 99% (z = 2.33) adds how much annual holding cost ?
- A. ₹342.50
- B. ₹685.00
- C. ₹822.50
- D. ₹1,165.00
Correct answer: A. ₹342.50
Extra safety stock = (2.33 − 1.645) × 50 = 34.25 units. Extra cost = 34.25 × 10 = ₹342.50. ₹1,165 is the whole 99% safety-stock cost, not the increase.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Which statement is true at the economic order quantity in the basic EOQ model?
- For an item ordered at its EOQ, the annual holding cost is ₹4,500. Annual demand is 9,000 units and each order costs ₹250. What is the…
- An item's reorder point is 500 units. Right now there are 320 units on hand, 300 units on an open purchase order and 20 units backordered…
- In a four-tier supply chain, the variance of weekly consumer demand is 100. The retailer's orders have variance 160, the distributor's…
- A batch of 500 circuit boards is inspected; each board has 4 opportunities for a defect. Inspectors find 30 defects. What is the DPMO?
- Defect counts last month: scratches 84, dents 56, misalignment 30, paint runs 18, other 12. Using Pareto analysis, what is the smallest…