Three activities have PERT estimates (optimistic, most likely, pessimistic) in days: P (2, 5, 14), Q (4, 6, 8), R (1, 8, 9). Which activity's duration is most uncertain, as measured by PERT variance?

  1. A. R, with variance about 1.78
  2. B. Q, with variance about 0.44
  3. C. R, because its most likely time is the longest
  4. D. P, with variance 4

Correct answer: D. P, with variance 4

PERT variance = ((b − a)/6)²: P = (12/6)² = 4, Q = (4/6)² ≈ 0.44, R = (8/6)² ≈ 1.78. Uncertainty depends on the spread between optimistic and pessimistic times, not on the most likely value.