Three activities have PERT estimates (optimistic, most likely, pessimistic) in days: P (2, 5, 14), Q (4, 6, 8), R (1, 8, 9). Which activity's duration is most uncertain, as measured by PERT variance?
- A. R, with variance about 1.78
- B. Q, with variance about 0.44
- C. R, because its most likely time is the longest
- D. P, with variance 4
Correct answer: D. P, with variance 4
PERT variance = ((b − a)/6)²: P = (12/6)² = 4, Q = (4/6)² ≈ 0.44, R = (8/6)² ≈ 1.78. Uncertainty depends on the spread between optimistic and pessimistic times, not on the most likely value.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- An LP has the constraints x + y ≤ 10, x ≤ 6 and 2x + 2y ≤ 30, with x, y ≥ 0. Which constraint is redundant?
- Three workers must be assigned to four jobs, one job each at most, to minimise cost. How should the Hungarian method be applied?
- A firm surveys customers by first dividing them into regions and then randomly sampling within each region in proportion to its size. What…
- Across 1,000 customers, the correlation between app sessions and spend is r = 0.3, with p < 0.001. Which interpretation is correct?
- A batch of 500 components comes from a process with a 0.4% defect rate. Using the Poisson approximation, what is the probability that the…
- =VLOOKUP("Pune", A2:B50, 2, FALSE) returns #N/A, although the sheet visibly shows 'Pune' in A17. The data were pasted from another system…